Why would %Complete different in Project Center from Details View?

K

kahuna

Any tips appreciated. I have a case of one of my projects showing up in
Project Center with 25% complete and when you click Edit and open the
project, it opens up in the Details view and the same field shows 26%
complete. When in Project Pro too, it shows up with 26%, so the project
center view is showing it differently.
 
K

kahuna

Figured this out to be some unlinked tasks that are summated in the overview
but not at the detail level. Not an issue anymore.
 