Why would the BCWS field be 0.00?

E

Elle

There are resources set so should this field automatically generate the cost
scheduled?

Thanks
 
G

Gérard Ducouret

Elle,
BCWS and other Earned Values data need 2 references : a Baselien and a
Status date. Did you set these 2 references?
Gérard
 