saeed
we created 2 calendars and we assign each calendar to separate tasks in the same summary task, one of the calendar just have 2 working days (Monday, Tuesday) and other calendar have 3 working days( Monday, Tuesday and Wednesday) when we review working hours for each member (resources) from task usage is correct but when we publish the project when we review the resources availability we found the calendar is not correct and starting with wrong days