Wierd Percent Allocation

N

Newbie

Hi,
In his timesheet, a resource entered 1d of Actual Work for Monday 12th June.
After validation and update, this data appears as 100% in the Task Usage
view of Project Pro (Percent Allocation field is displayed). OK.
In his timesheet, the same resource entered 0.5d for Tuesdays 13th June.
This data appears as 50% in the Task Usage view of Project Pro. OK
The resource entered 0 for the 2 following days: 0%
The resource entered 1d Actual Work on Friday (The last day of the task)
and the Task Usage view displays 127% Percent Allocation.
Now the Peak Units of that resource on that task is 1.27 !
Thanks for any hint!
 
G

Gary L. Chefetz [MVP]

Newbie:

On its face, this would indicate that one day is 27% more work than
originally scheduled for that day.
 