G
Gene
I am trying to find the best (or at least a good) way of scheduling a
"window". I have a task that I want to allocate 16 hours (2 work
days) labor for, but the task may be done any time during a five day
period (single work week). IOW, 5 days time set aside for 2 days
labor.
Both are estimates, the actuals will be completed as the tasks are
done.
"window". I have a task that I want to allocate 16 hours (2 work
days) labor for, but the task may be done any time during a five day
period (single work week). IOW, 5 days time set aside for 2 days
labor.
Both are estimates, the actuals will be completed as the tasks are
done.