A known quantity of men is allocated to each task in a complicated schedule
in which many tasks overlap. How can I establish the total number of men
required each week.
 
R

Rod Gill

Hi,

Select View, Resource usage. Zoom out until the timescale is weekly then
read the total hours for each week. You can also right click the yellow area
and select Peak Units.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.project-systems.co.nz/
Email rodg AT project-systems DOT co DOT nz
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top