Wizard to Tranfer Assignments across many projects

W

Wegz

Hi, Is there a way to transfer all of Mr A's assignments to Mr B in a
quick and easy way. The only way i have seen is to go into each
project, select Mr A's tasks, select the replace option and choose Mr
B. Is there a quicker way (assuming we have been slack and not set up
correctly all the skills and other data describing staff)

Thanks, Matt
 
D

Dale Howard [MVP]

Matt --

There's no way any easier than what you have already figured out. Sorry.
 
K

Kaman

Related question. After the replacement and subsequently publishing, should
the tasks be removed automatically from Mr. A's list? I have a user who
complains that the tasks are still showing up on her list.

Thanks,

Kaman
 
D

Dale Howard [MVP]

Kaman --

The tasks will continue to show up on Mr. A's timesheet as cancelled tasks
with a big black X indicator to the left of the task name. Mr. A should
select each cancelled task and click the Hide button to remove them from the
timesheet. Hope this helps.
 