won't calculate

S

swell estimator

I know enough to check under Tools/Options/Calculate and I've experimented
with automatic and manual and I can't get tasks to recalculate.

I've been able to get my tasks to calculate before but on a different
computer.

If I use the Predecessor tab in Information to create a successor, the
successor shows properly but it won't calculate. I having this problem
through-out my schedule. Sometimes it calculates and other times it doesn't .

Please advise ASAP. Thank you. Chris
 
R

Rod Gill

Hi,

Two things may be happening, one your links are conflicting. is there an
error message in the status bar at the bottom of the screen?
Two you have dates on tasks that prevent Project moving them.
Select both tasks then press Shift+F2 to open the Task Information dialog.
Click the Advanced tab and select Type As Soon as Possible
Ok

Now see if the link moves the second task.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
J

JulieS

Hi swell estimator,

To add to Rod and Jan's excellent suggestions, I would also check
and make sure that the successor tasks don't have Actual Start
dates. View the Tracking Table and ensure that tasks do not have an
actual start.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

in message
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top