"work†field displayed days not hours for my resources in View Tas

J

Jaya

In PS 2003,MS project plan by changing the way that the Work unit is displayed

1.On the Tools menu, click Options, and then click the Schedule tab.
2.In the Work is entered in box, select the time unit as days.
3.make the new settings the default in future projects, click Set as Default.
4.Publish the project to server

It wont get reflected in view my tasks in webclient.

Finally I created a new test project plan and assign myself some tasks
and publish it.This works fine i can see work field as days not in hours in
view my tasks in web access.But i want to display the same thing for old
projects plans also.

Please give me assistance
 
J

John

Jaya said:
In PS 2003,MS project plan by changing the way that the Work unit is
displayed

1.On the Tools menu, click Options, and then click the Schedule tab.
2.In the Work is entered in box, select the time unit as days.
3.make the new settings the default in future projects, click Set as Default.
4.Publish the project to server

It wont get reflected in view my tasks in webclient.

Finally I created a new test project plan and assign myself some tasks
and publish it.This works fine i can see work field as days not in hours in
view my tasks in web access.But i want to display the same thing for old
projects plans also.

Please give me assistance

Jaya,
This question will probably get a quicker response if posted in our
sister newsgroup, microsoft.public.project.server. This newsgroup is
dedicated to the stand alone versions of Project.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top