J
Jaya
In PS 2003,MS project plan by changing the way that the Work unit is displayed
1.On the Tools menu, click Options, and then click the Schedule tab.
2.In the Work is entered in box, select the time unit as days.
3.make the new settings the default in future projects, click Set as Default.
4.Publish the project to server
It wont get reflected in view my tasks in webclient.
Finally I created a new test project plan and assign myself some tasks
and publish it.This works fine i can see work field as days not in hours in
view my tasks in web access.But i want to display the same thing for old
projects plans also.
Please give me assistance
1.On the Tools menu, click Options, and then click the Schedule tab.
2.In the Work is entered in box, select the time unit as days.
3.make the new settings the default in future projects, click Set as Default.
4.Publish the project to server
It wont get reflected in view my tasks in webclient.
Finally I created a new test project plan and assign myself some tasks
and publish it.This works fine i can see work field as days not in hours in
view my tasks in web access.But i want to display the same thing for old
projects plans also.
Please give me assistance