Bobg
I let Project schedule tasks at a high level, but when tracking what
resources will be working on for a given week, I often go to the Resource
Usage View and manually edit the work assignments to properly reflect what
each resource is working on for a given week. I enter work hours manually at
that point all the way to the expected end of the task (even if it goes
beyond the week we are currently working on). I have noticed that there are
times when the % work complete keeps increasing even when I am entering work
hours for future weeks. When I display the actual work fields, I have noticed
that every time I enter Work, Actual Work gets filled in as well. If I delete
one, it deletes the other.
How can I manually enter the hours that I plan on a resource working on a
task without affecting actual work, and therefore my percent work complete?
Thank you for the help.
Bob
resources will be working on for a given week, I often go to the Resource
Usage View and manually edit the work assignments to properly reflect what
each resource is working on for a given week. I enter work hours manually at
that point all the way to the expected end of the task (even if it goes
beyond the week we are currently working on). I have noticed that there are
times when the % work complete keeps increasing even when I am entering work
hours for future weeks. When I display the actual work fields, I have noticed
that every time I enter Work, Actual Work gets filled in as well. If I delete
one, it deletes the other.
How can I manually enter the hours that I plan on a resource working on a
task without affecting actual work, and therefore my percent work complete?
Thank you for the help.