J
Jose X Perez
Hi everyone,
In a project server 2007 enviroment I create a mcra tha uses the event
ProjectBeforeTaskChange but when i save a project for the first time i get
the error Error 458: Variable uses an automation type not supported in Visual
Basic so in order to fix this problem i installed the kb 941657
But now when i assign a resource to a task and she send an actualization to
the project manager, the work distribution to the task changes and the %
complete and % work complete varies.
for example
i have a task1 assigned to Gina duration is 1d and work 8h.
start 10/27 8:00, finish 10/27 18:00
Standard Calendar monday to friday 8:00-13:00 and 15:00-18:00.
In my tasks page of Gina she reports 20% of progress, for the task1, but
when the project manajer apply the change to the schedule the % complete
shows 36% and the % work complete shows 20%, the duration changes to 1.25
days work stay in 8h.
When i dont use the post service pack 941657 i get the first error but
everythin else works fine.
I search for a newer hotfix for this issue but i dont find one, i already
try 950480 and 953751.
Any help or i must wait for the service pack 2?
Thank you,
José X Pérez
In a project server 2007 enviroment I create a mcra tha uses the event
ProjectBeforeTaskChange but when i save a project for the first time i get
the error Error 458: Variable uses an automation type not supported in Visual
Basic so in order to fix this problem i installed the kb 941657
But now when i assign a resource to a task and she send an actualization to
the project manager, the work distribution to the task changes and the %
complete and % work complete varies.
for example
i have a task1 assigned to Gina duration is 1d and work 8h.
start 10/27 8:00, finish 10/27 18:00
Standard Calendar monday to friday 8:00-13:00 and 15:00-18:00.
In my tasks page of Gina she reports 20% of progress, for the task1, but
when the project manajer apply the change to the schedule the % complete
shows 36% and the % work complete shows 20%, the duration changes to 1.25
days work stay in 8h.
When i dont use the post service pack 941657 i get the first error but
everythin else works fine.
I search for a newer hotfix for this issue but i dont find one, i already
try 950480 and 953751.
Any help or i must wait for the service pack 2?
Thank you,
José X Pérez