Steve Scott
I have a Deliverable consisting of ten tasks. Becuase this Deliverable is in
a latter stage of my project I only want to be able to estimate effort at the
Deliverable level only. Is there anyway way I can enter a work value at the
Deliverable (summary task) level only ie not have to put values in each of
the ten tasks for it to summ up? I suppose I am really looking for the
"work" column at summary level to act in the same way that %Work complete
does in that one can add a value at summary level and it spreads that value
out amongst the tasks below it.
I have toyed with the idea of using a custom duration column to show the
estimate effort for the deliverable which is fine but I dont think I can
connect my end stage milestone to it - ie that would still come at the end of
the last task within the deliverable.
a latter stage of my project I only want to be able to estimate effort at the
Deliverable level only. Is there anyway way I can enter a work value at the
Deliverable (summary task) level only ie not have to put values in each of
the ten tasks for it to summ up? I suppose I am really looking for the
"work" column at summary level to act in the same way that %Work complete
does in that one can add a value at summary level and it spreads that value
out amongst the tasks below it.
I have toyed with the idea of using a custom duration column to show the
estimate effort for the deliverable which is fine but I dont think I can
connect my end stage milestone to it - ie that would still come at the end of
the last task within the deliverable.