A
aschmidt
Is there a way to stop "work" attributing to resources' "actual work" when a
task is marked 100% complete? I want entered actuals to stand as total actual
work rather than adding scheduled work not zeroed out.
Setting the remaining work to zero does the same thing that marking a task
100% complete does - attributes the scheduled hours as actual.
When a project updates from the timesheet in PWA and a project manager
accepts the time entered AND 0 remaining work (entered by the team member in
the timesheet), the scheduled work is attributed to the task unless a zero is
entered by the resource in the timesheet for the day on which work was
originally scheduled.
So far, the only way to get around this is to have the project
manager check updates in the project prior to accepting or
requiring resources enter zeros for scheduled work not completed.
task is marked 100% complete? I want entered actuals to stand as total actual
work rather than adding scheduled work not zeroed out.
Setting the remaining work to zero does the same thing that marking a task
100% complete does - attributes the scheduled hours as actual.
When a project updates from the timesheet in PWA and a project manager
accepts the time entered AND 0 remaining work (entered by the team member in
the timesheet), the scheduled work is attributed to the task unless a zero is
entered by the resource in the timesheet for the day on which work was
originally scheduled.
So far, the only way to get around this is to have the project
manager check updates in the project prior to accepting or
requiring resources enter zeros for scheduled work not completed.