T
Tony K
I work for a company that provides engineering services to multiple clients
which is billed at an hourly rate to our clients.
We have recently purchased the MSP 2003 software to provide scheduling
management of our multiple projects based on hours (work) available from our
four resources.
Our intent is to schedule our projects based on a fixed length of time for
example one week. Our four resources are available for 45 hours each per week
which totals 180 hours. (work)
What advice can be shared for the set up of our project tasks that will
allow me to enter the start and finish dates for one week? Then assign our
four resources (work) to the task for that week? Then if I shorten or
lengthen the finish date of the task the percentage of our four resources
will adjust automatically increasing or decreasing based on the work I
assigned originally?
Basically I want to schedule based on (work) hours of the four resources not
by duration hours. In fact the duration based column and functionality does
not work with our work flow. We know that we have 180 hours per week to
schedule and if a task requires more resources then we can assign our
resources accordingly.
I hope this makes sense to someone that understands how MSP 2003 works.
Again I am new to this software and have been attempting to learn it on my
own with more frustration than progress.
Thanks in advance!
which is billed at an hourly rate to our clients.
We have recently purchased the MSP 2003 software to provide scheduling
management of our multiple projects based on hours (work) available from our
four resources.
Our intent is to schedule our projects based on a fixed length of time for
example one week. Our four resources are available for 45 hours each per week
which totals 180 hours. (work)
What advice can be shared for the set up of our project tasks that will
allow me to enter the start and finish dates for one week? Then assign our
four resources (work) to the task for that week? Then if I shorten or
lengthen the finish date of the task the percentage of our four resources
will adjust automatically increasing or decreasing based on the work I
assigned originally?
Basically I want to schedule based on (work) hours of the four resources not
by duration hours. In fact the duration based column and functionality does
not work with our work flow. We know that we have 180 hours per week to
schedule and if a task requires more resources then we can assign our
resources accordingly.
I hope this makes sense to someone that understands how MSP 2003 works.
Again I am new to this software and have been attempting to learn it on my
own with more frustration than progress.
Thanks in advance!