R
Rick
I'm changing the % Work Complete in Project Professional and then
republishing the plan via Publish All Information, but the changes are not
reflected in the Timesheet view in PWA.
o Using Republish Assignments does not resolve this either
o I know the republish is working to a certain extent because if I add a
new task, that shows up.
o Interestingly enough, the change to % Work Complete is properly reflected
in the Project Center views.
Anyone know why a change to % Work Complete in Project Professional would
not be reflect in the Timesheet view?
republishing the plan via Publish All Information, but the changes are not
reflected in the Timesheet view in PWA.
o Using Republish Assignments does not resolve this either
o I know the republish is working to a certain extent because if I add a
new task, that shows up.
o Interestingly enough, the change to % Work Complete is properly reflected
in the Project Center views.
Anyone know why a change to % Work Complete in Project Professional would
not be reflect in the Timesheet view?