Here's some additional information from the "HelP" that will further explain
Steve's Post. My post assumed the box as checked as this is the default.
If this check box is cleared, you must enter values in the Actual Work field
for resources in order to have an accurate picture of the actual work and
actual cost. By default, this check box is selected.
Whether this check box is selected or cleared, once a task is 100 percent
complete, work on assignments is also marked complete.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
Steve House said:
Go to the Tools / Options menu. On the Calculation tab, clear the checkbox
for "Updating task status updates resource status."
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
MPH said:
How do you prevent an update in one of the columns (% work complete) from
updating the other (% Complete) with the same vaule and vice versa. I
want
differnet statuses reflected in each column and I cannot get to stop
reflecting the same??