M
MahirK
hi all,
% work comlete field is automaticly updating when team members fill their
own timesheet. Project manager doesnt want somethig which is automaticly
updated. On the other hand, for a task, team member can work more then planed
hours and it doesnt mean that that task is completed. Thats why, we want to
use physical complete field.
what should I do for this problem?
Thanks in advance,
best regards
% work comlete field is automaticly updating when team members fill their
own timesheet. Project manager doesnt want somethig which is automaticly
updated. On the other hand, for a task, team member can work more then planed
hours and it doesnt mean that that task is completed. Thats why, we want to
use physical complete field.
what should I do for this problem?
Thanks in advance,
best regards