%work complete - Roll up

Joined
Jul 1, 2024
Messages
1
Reaction score
0
Since the %completion changes when I change the Finish Date, I am trying to create a % work complete column where the high level activities would have their % work completed calculated using averaging the subtasks. How can I do this? (I tried to make sure that the roll up box is ticked for the task but still doesnt work)
 