S
Shahriar Nour Khondokar
I have created a project plan and then set a baseline.
After that for each task that has been completed, i have entered Actual Work
value, which in turn updated the Work column (when Actual is greater or less
than baseline) and the %Work Complete column (for the whole project).
What i need is the % Work Complete calculated based on the baseline plan. In
other words I would like to know when a task is marked as 100%complete, how
much of the baseline work is complete (along with % Work Complete based on
Actual Work input, found in the '% Work Complete' column).
Is there a built in column in MS Project where this data is stored?
After that for each task that has been completed, i have entered Actual Work
value, which in turn updated the Work column (when Actual is greater or less
than baseline) and the %Work Complete column (for the whole project).
What i need is the % Work Complete calculated based on the baseline plan. In
other words I would like to know when a task is marked as 100%complete, how
much of the baseline work is complete (along with % Work Complete based on
Actual Work input, found in the '% Work Complete' column).
Is there a built in column in MS Project where this data is stored?