D
David Oliver
It seems to me that there is a lot of tension between the
concept of duration and the concept of work in MSP. I
imagine that MSP was originally designed to work with
duration only and that work was an afterthought, which
has still never been fully integrated into the product.
MS, for example, allows you to enter and update duration
and % Complete through the Task Information and the
Update Tasks dialog box, but not Work & %WorkComplete!
And MSP uses % Complete to calculate earned value (SPI,
CPI) rather than %WorkComplete, which seems ludicrous. I
really expected that they would use % Work Complete for
this calculation, since earned value is all about WORK:
planned, burned and earned. And %Work Complete can be a
radically different value than the % Complete on projects
at any given point in time. WORK is cumulative (a real
sum) under the project summary task, whereas duration is
not!
As must be apparent, I've got some real frustration about
the way MSP deals with these concepts, so if you know of
any papers that elucidate this problem, I'd love to know
about them. It seems like the MSP team has been avoiding
or patching a problem when they really ought to
completely revamp their approach to statusing projects.
Why can't we enter actual work and remaining work through
the Update Task dbox, for example. Is it that MSP code
won't support it? Why not? Why do they keep asking
about remaining duration instead of remaining work?
I'd be glad to hear anyone's thoughts on the subject, as
well as to hear about any MS white papers or papers from
other sources that clarify what seems like a big problem
to me. I may be wrong, but I smell a rat buried in the
MSP woodwork. It may be that I just haven't grasped it
yet. Very possible. I'm interested in hearing other
ideas on this subject.
Sincerely,
Dave Oliver
concept of duration and the concept of work in MSP. I
imagine that MSP was originally designed to work with
duration only and that work was an afterthought, which
has still never been fully integrated into the product.
MS, for example, allows you to enter and update duration
and % Complete through the Task Information and the
Update Tasks dialog box, but not Work & %WorkComplete!
And MSP uses % Complete to calculate earned value (SPI,
CPI) rather than %WorkComplete, which seems ludicrous. I
really expected that they would use % Work Complete for
this calculation, since earned value is all about WORK:
planned, burned and earned. And %Work Complete can be a
radically different value than the % Complete on projects
at any given point in time. WORK is cumulative (a real
sum) under the project summary task, whereas duration is
not!
As must be apparent, I've got some real frustration about
the way MSP deals with these concepts, so if you know of
any papers that elucidate this problem, I'd love to know
about them. It seems like the MSP team has been avoiding
or patching a problem when they really ought to
completely revamp their approach to statusing projects.
Why can't we enter actual work and remaining work through
the Update Task dbox, for example. Is it that MSP code
won't support it? Why not? Why do they keep asking
about remaining duration instead of remaining work?
I'd be glad to hear anyone's thoughts on the subject, as
well as to hear about any MS white papers or papers from
other sources that clarify what seems like a big problem
to me. I may be wrong, but I smell a rat buried in the
MSP woodwork. It may be that I just haven't grasped it
yet. Very possible. I'm interested in hearing other
ideas on this subject.
Sincerely,
Dave Oliver