% work complete vs % complete

T

Tina

My resources are updating % work complete in PWA. I've noticed that after
accepting the changes, the % work complete in Project Plan remains at 0%, yet
if I look at the project in PWA, the % work complete is correct. Why doesn't
the Project Plan get updated? I've looked through all the posts and the
common thread I see is making sure I have "Updating Task Status Updates
Resource Status" checked off, which I have done. It's almost like PWA is ok
but Project Plan doesn't want to reflect the changes made. Why would that be?

Thanks!
 
T

Tina

Dale,

Thanks but I've been through this already. This check box was already a
default from the beginning of the project. It's always been checked. I
don't understand how the changes to % work complete from web access remain in
web access, even after I've published from the project plan, yet the % work
complete does not show up in project plan. This is getting really
frustrating.

Thanks!
 
D

Dale Howard [MVP]

Tina --

Please ask your Project Server administrator to determine is there are
errors in the server's application error log and then report your findings
in this group as a separate post if there are errors. Let us know.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top