Work % Complete

J

Jason

Hello,
I'm in PWA (2007)/ My Tasks, and update a task by changing the "work %
Complete" to 100%. Then I go through the submitt and approval process. Now,
If I try to view that task in a project view or project center, I see no
update. However, if i bring up Project Professional and re publish, then I
can see the 100% complete in the various view. I notice that this test is
true regardless of what I undate (Actual work, remaining work, etc..

Is this a bug or functionality by design? Thanks, Jason
 
D

Dale Howard [MVP]

Jason --

This is not a bug. After processing task updates into the Microsoft Project
plan, the PM must open the project and publish the latest schedule changes
before the information becomes visible in PWA. Hope this helps.
 
J

Jason

As always Dale... Thanks!


Dale Howard said:
Jason --

This is not a bug. After processing task updates into the Microsoft Project
plan, the PM must open the project and publish the latest schedule changes
before the information becomes visible in PWA. Hope this helps.
 