J
Jason
Hello,
I'm in PWA (2007)/ My Tasks, and update a task by changing the "work %
Complete" to 100%. Then I go through the submitt and approval process. Now,
If I try to view that task in a project view or project center, I see no
update. However, if i bring up Project Professional and re publish, then I
can see the 100% complete in the various view. I notice that this test is
true regardless of what I undate (Actual work, remaining work, etc..
Is this a bug or functionality by design? Thanks, Jason