Hi,
Do these tasks, that should have percent complete figures but are showing
0%, have any resource assigned ?
Gérard Ducouret
Mary Ann said:
Hi -
I arrived at this view by using 'Track' in the Project Guide, then 'Check
the progress of the project'. %work completed is one of the columns I'm
using in the Gantt Chart. After invoking 'Check the progress' I realized
that this view was not reflecting some of the percentages of work completed
shown in the Gantt view. Majority of the % Work Completed was shown
accurately, however several tasks that should have percent complete figures
showed 0%.