S
Sarah M-H
Our client is under contract to complete a project in 540
CALENDAR days.
Our project schedule, which is based on working 8 to 5, M-
F, calculates the project duration as 355 WORK days.
It would be nice if the duration included weekends so
that it showed up as 540 calendar days. Is this possible?
CALENDAR days.
Our project schedule, which is based on working 8 to 5, M-
F, calculates the project duration as 355 WORK days.
It would be nice if the duration included weekends so
that it showed up as 540 calendar days. Is this possible?