Work days

B

Bob Freeman

Hello,

I am trying to get a formula that will calculate the number of workdays
(Monday to Friday) between two dates in the following format - if possible
this will also take into account a specified list of holidays (non-workdays),
e.g. 25/12/08, which I can specify in a list.

This will always revolve around date 1 - so if date 2 is after date 1 it
will be a positive number, if date 2 is before date one, it will be a
negative number

For example:

Date 1 Date2 No of working
days from date 1

Monday 2nd Feb Friday 30th Jan -1
Monday 2nd Feb Wednesday 4th Feb 2
Monday 2nd Feb Monday 9th Feb 5


Many thanks.

Bob
 
K

Kevin B

Use the =NETWORKDAYS(Start_Date,End_Date,[Holidays])

Holidays are an optional entry, where start and end dates are required.
 
M

Mike H

Hi,

Networkdays would normally give an answer 1 higher than you are asking for
so perhaps this

=IF(B1<A1,networkdays(A1,B1,Holidays)+1,networkdays(A1,B1,Holidays)-1)

If your results are an error or typo use the simpler

=networkdays(A1,B1,Holidays)

Holidays is a named range containing holiday dates. If you get a NAM error
then
Tools|Addins and load the analysis toolpak.

Mike
 
B

Bob Freeman

Thanks Mike - this is great

Mike H said:
Hi,

Networkdays would normally give an answer 1 higher than you are asking for
so perhaps this

=IF(B1<A1,networkdays(A1,B1,Holidays)+1,networkdays(A1,B1,Holidays)-1)

If your results are an error or typo use the simpler

=networkdays(A1,B1,Holidays)

Holidays is a named range containing holiday dates. If you get a NAM error
then
Tools|Addins and load the analysis toolpak.

Mike
 
B

Bob Freeman

Thank you

Kevin B said:
Use the =NETWORKDAYS(Start_Date,End_Date,[Holidays])

Holidays are an optional entry, where start and end dates are required.
--
Kevin Backmann


Bob Freeman said:
Hello,

I am trying to get a formula that will calculate the number of workdays
(Monday to Friday) between two dates in the following format - if possible
this will also take into account a specified list of holidays (non-workdays),
e.g. 25/12/08, which I can specify in a list.

This will always revolve around date 1 - so if date 2 is after date 1 it
will be a positive number, if date 2 is before date one, it will be a
negative number

For example:

Date 1 Date2 No of working
days from date 1

Monday 2nd Feb Friday 30th Jan -1
Monday 2nd Feb Wednesday 4th Feb 2
Monday 2nd Feb Monday 9th Feb 5


Many thanks.

Bob
 