S
SusanB
I'm new to project and have MS Project Standard 2002. I have a Project file I
inherited from someone else. The tasks, start, finish, work, duration,
predecessors, and resource names fields are complete, mostly.
One of the tasks was started almost 6 months ago, assigned to two people who
used 32 of 40 hours on it, and now it must be completed by two different
people, starting tomorrow. I'm trying to tell Project that the start date was
9/4/07, percent complete is 80, and that the remaining work will start
tomorrow, but I'm having no luck. Is it possible to say "Joe spent 8 hours,
Mary spent 24 hours, and now Jack will spend 2 hours and Jill will spend 6
hours and the thing will be done?"
inherited from someone else. The tasks, start, finish, work, duration,
predecessors, and resource names fields are complete, mostly.
One of the tasks was started almost 6 months ago, assigned to two people who
used 32 of 40 hours on it, and now it must be completed by two different
people, starting tomorrow. I'm trying to tell Project that the start date was
9/4/07, percent complete is 80, and that the remaining work will start
tomorrow, but I'm having no luck. Is it possible to say "Joe spent 8 hours,
Mary spent 24 hours, and now Jack will spend 2 hours and Jill will spend 6
hours and the thing will be done?"