Work effort per ressource group in gant

W

winz

Hi,

On my tasks I have internal and external ressources allocated.
e.g. internal work 5 days
external work 10 days

In my Gant view I would like to see two columns. One that shows me the
internal work effort, one that shows me the external work effort. The
current work field shows me the total (15 days).

Any one an idea how this is possible?

Thanks in advance - Chris
 
R

Rod Gill

You can create some formulae in custom fields like Number1 to do this, or
you can have Internal or External in the Resource Group column and in a
Gantt chart apply the [Resource Group] Group.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top