E
edilvo
Hi...
I have tried to use MSProject 2000 by ODBC, because I need to integrate another system to it. When I fill, in msp_tasks, duration fields (task_dur, task_act_dur,...), it works well and shows the values correctly. But work fields (task_work, task_act_work,...) haven't, because MSProject changes the values that I filled in table.
Is this a parameter misunderstanding?
Thank you
I have tried to use MSProject 2000 by ODBC, because I need to integrate another system to it. When I fill, in msp_tasks, duration fields (task_dur, task_act_dur,...), it works well and shows the values correctly. But work fields (task_work, task_act_work,...) haven't, because MSProject changes the values that I filled in table.
Is this a parameter misunderstanding?
Thank you