C
Craig
I like to use the resource and task usage views, but for the resource view it
does not roll up the resource work for each summary task. We have to put
together several design packages and each design package has a WBS of 1.1,
1.2 1.3 ... etc. I want to be able to see what the costs or work is for each
of the level two tasks ( or in this case design package). The only way I can
do it now is to manually sum up the resource usage view for each summary
task. I would think you should have the option to show the summary tasks
also...
Thanks,
does not roll up the resource work for each summary task. We have to put
together several design packages and each design package has a WBS of 1.1,
1.2 1.3 ... etc. I want to be able to see what the costs or work is for each
of the level two tasks ( or in this case design package). The only way I can
do it now is to manually sum up the resource usage view for each summary
task. I would think you should have the option to show the summary tasks
also...
Thanks,