C
CK
Hi,
I have 3 shifts covering a 24 hour period. I created calendars for each
shift. When I assign a 1st shift resource to a 12 hour duration task the
calculated work is 12 hours. However, when I assign a second shift resource
(effort driven on and type is units) the hours are split evenly 6 hrs each.
Is there a way for Project to automaticaly recognize that the 1st shift
completed their 8 hour day and then the 2nd shift picks up the other 4 hours?
I know I can change the work hours manually but I would like the work to
flow from one shift to the next -- I do not want Project to evenly distribute
the work time. I tried work contontour but that doesn't seem to work the way
I expected.
Thanks for any help you can provide.
I have 3 shifts covering a 24 hour period. I created calendars for each
shift. When I assign a 1st shift resource to a 12 hour duration task the
calculated work is 12 hours. However, when I assign a second shift resource
(effort driven on and type is units) the hours are split evenly 6 hrs each.
Is there a way for Project to automaticaly recognize that the 1st shift
completed their 8 hour day and then the 2nd shift picks up the other 4 hours?
I know I can change the work hours manually but I would like the work to
flow from one shift to the next -- I do not want Project to evenly distribute
the work time. I tried work contontour but that doesn't seem to work the way
I expected.
Thanks for any help you can provide.