Work hours not adding up

J

Joe

I have a summary task with 3 sub task under it.
The "work" for the 3 task are as follows:

task A 2hrs.
task B 3hrs.
task C 3hrs.

Why am I geting total "work" of 11 hrs.? I understand why
I am gettign 3 hrs. for the duration, but don't undertsand
why I am not getting 8hrs. for the work (at the summary
level).

Joe
 
G

Guest

I's liek to add that there were two resources assigne with
less than 100% allocations to each, but I deleted that. I
found when I deleted the entire task and re-entered them
it was okay. But I have many adjustments to make, why
would this happen, and why should that affect the work, I
understand duration, but not work.
 
R

Rod Gill

Hi,

Has a resource been assigned to the summary task as well? That is one
explanation.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top