Work load

L

lk50

I have a single master plan with a number of different projects in it.
The same resources are working on all the projects. In the resourc
usage view I want see how many days each resource is working on
particular project on a monthly basis.

So for example I want to see:

HR
May June July
Joe Bloggs 15d 10d 12d

Marketing

Joe Bloggs 5d 3d 4d

In the Gantt chart view I added a text1 field with the project name an
then tried to filter it in the resource usage view but it doesn’
display in the resource usage view

Hope this make sense

Many thank
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top