M
Mask
Hello,
We are using Ms Project Professional 2007 and Ms Project Server 2007.
Problem: Working hours (work) in mpp are diferent from planned Work in
Timesheet.
Example: in .mpp we have assignd a resource to a task, defined the
duration and planned 5h work each day in a week. After that we
published the .mpp. When the resource open My Timesheet in PWA it
appears something like 4,857h per day. When we open the .mpp the plan
is correct.
Resolution applied: We thought that could be a problem with Calendar
so we applied Calendar to the Plan and cleared the calendar that was
applied to the resource. It didn't resolved.
Any suggestion?
Thx in advance,
Best Regards,
Mask
We are using Ms Project Professional 2007 and Ms Project Server 2007.
Problem: Working hours (work) in mpp are diferent from planned Work in
Timesheet.
Example: in .mpp we have assignd a resource to a task, defined the
duration and planned 5h work each day in a week. After that we
published the .mpp. When the resource open My Timesheet in PWA it
appears something like 4,857h per day. When we open the .mpp the plan
is correct.
Resolution applied: We thought that could be a problem with Calendar
so we applied Calendar to the Plan and cleared the calendar that was
applied to the resource. It didn't resolved.
Any suggestion?
Thx in advance,
Best Regards,
Mask