Work on Weekends

G

Guest

I have been trying to change the working time calendar
for a resource to allow work on weekends. I can make the
changed to the calendar but project98 will still not show
the work being done on weekend. It moves the task to the
next week day. What am I doing wrong?

TIA

Thom in Texas
 
R

Rod Gill

Hi,

Tasks without resources use the Standard calendar. Edit the standard
calendar and by default, the same edits are duplicated in all resource
calendars.

If a resource is assigned to a task, its calendar is used to determine what
hours are working.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
D

Dave W

You have to tell that task in the task information to use the calendar you
set up instead of the default calendar. Look in Task Information.
 