I have an odd thing happenning ...I have Work & Remaining Work in my
schedule displaying in 'Days'...(This is also the setting on the Global
Template; as set from Tools|Options|Schedule settings).
However, when this schedule & others too are viewed vis PWA...these columns
are displayed in 'Hours'..
While I realise that this is not the end of the world - it IS very annoying
to my PM's...
Where can I change this to display in 'Days' in PWA...
As ever, all help greatly appreciated.
I have an odd thing happenning ...I have Work & Remaining Work in my
schedule displaying in 'Days'...(This is also the setting on the Global
Template; as set from Tools|Options|Schedule settings).
However, when this schedule & others too are viewed vis PWA...these columns
are displayed in 'Hours'..
While I realise that this is not the end of the world - it IS very annoying
to my PM's...
Where can I change this to display in 'Days' in PWA...