W
WillW
One of the project managers I work with showed me a project schedule into
which she has begun entering task estimates; she asked why the totals of most
rollup-level tasks are wrong. For example (this is one of many), a group
task has 3 sub-tasks of 2 days work each. But the roll-up total is 8 days.
I can't explain it. Where do I look? What am I missing?
Thanks,
Bill
which she has begun entering task estimates; she asked why the totals of most
rollup-level tasks are wrong. For example (this is one of many), a group
task has 3 sub-tasks of 2 days work each. But the roll-up total is 8 days.
I can't explain it. Where do I look? What am I missing?
Thanks,
Bill