Hi. I am facing a problem with project server 2007:
Sometime into the project, the PM is notified he can use another
resource. He adds the new resource (build team from enterprise), and
assigns him to some already-existing tasks.
The problem is after "resource leveling" the assignment is scheduled
for the past, to a date that the resource was not available to the
project.
What should the PM do so Project will schedule tasks for this resource
only in the future?
Thanks for the help,
Gil