J
Jarvis
I am new to working with Project, so please forgive me if this is a dumb
question. I need to calculate the time required for a task is based on a
percentage of work from a different resource. Let me explain...
I have a Project Manager resource. We calculate the amount of time that the
PM figures into a project based on a percentage of the total time of other
resources working on the project. The PM's time should be 20% of the combined
time of Resource1 and Resouce2 for a given phase of the project.
Is this possible?
Thanks in advance,
Jarvis
question. I need to calculate the time required for a task is based on a
percentage of work from a different resource. Let me explain...
I have a Project Manager resource. We calculate the amount of time that the
PM figures into a project based on a percentage of the total time of other
resources working on the project. The PM's time should be 20% of the combined
time of Resource1 and Resouce2 for a given phase of the project.
Is this possible?
Thanks in advance,
Jarvis