B
Bill Cole
I'm using Project 2003 and Project Server.
I plug resources in at some percent less than 100% to account for support
time.
For example, a resource has a 10 day task which works out to 80 hours of
work.
When I plug the resource in at 90% on this task, Project shows 11.11 days
duration to complete the 80 hours of work. That much is fine.
The problem occurs when the resource updates his hours. When I accept the
hours he has submitted, I noticed the working units for many
of the tasks are messed up. I entered him for all tasks at 90% so I know
what the original percent of working units was. Now he is listed
fo rmany tasks at 100%, some at 125%, some at 150%, one at 83%.
The duration on one task no longer matches the total work. 16 hours of
total work. At 90% should take 2.2 days duration and this was
correct in the original published project. Project now shows 7 days
duration for this task. If I change the duration back to 2.22 days, it
shows the resource scheduled at 14%. It seems there is another variable in
the work/duration/working unit formula, and Project is changing
that other variable without me knowing about it. I cannot get back to the
original task values of 2.22 days duration & 16 hours work.
I have to delete the tasks and recreate it from scratch to fix it.
Has anyone seen similar problems with working units and duration values
getting changed when they shouldn't be? Is this a known problem.
I plug resources in at some percent less than 100% to account for support
time.
For example, a resource has a 10 day task which works out to 80 hours of
work.
When I plug the resource in at 90% on this task, Project shows 11.11 days
duration to complete the 80 hours of work. That much is fine.
The problem occurs when the resource updates his hours. When I accept the
hours he has submitted, I noticed the working units for many
of the tasks are messed up. I entered him for all tasks at 90% so I know
what the original percent of working units was. Now he is listed
fo rmany tasks at 100%, some at 125%, some at 150%, one at 83%.
The duration on one task no longer matches the total work. 16 hours of
total work. At 90% should take 2.2 days duration and this was
correct in the original published project. Project now shows 7 days
duration for this task. If I change the duration back to 2.22 days, it
shows the resource scheduled at 14%. It seems there is another variable in
the work/duration/working unit formula, and Project is changing
that other variable without me knowing about it. I cannot get back to the
original task values of 2.22 days duration & 16 hours work.
I have to delete the tasks and recreate it from scratch to fix it.
Has anyone seen similar problems with working units and duration values
getting changed when they shouldn't be? Is this a known problem.