F
FaisalM
We have seen a variation in work values in project plan & Portfolio Analyzer.
We are using Project Server 2003 with SP1 on Win2003.
Here are the details:
1. Resource A is assigned to different projects. Check this screenshot
http://tinypic.com/f0qd7o.jpg
We go to Resource Usage view, change the timescale to year / month. Now we
can see the resource's work hours by month (October 2005 - MArch 2006). He
has been assigned total of 854.25h in total. You can see that he has been
assigned 161, 152, 168 hours of work in Jan, Feb & march respectively.
2. Next I went to PWA > Resources > View Resource Assignments. Check this
screenshot
http://tinypic.com/f0qbgx.jpg
I selected the same resource in Summary view. Now I can see his work across
all plans for all months. Which is 856.88h. Thats fine.
3. Next I went to PWA > Resources > View Enterprise Resources in Resource
Center. Check this screenshot:
http://tinypic.com/f0qdcn.jpg
In Assignment work by Resource view I entered time period from 10/1/2005 to
03/31/2006. In details table below I can see his work as 854.2h, which is
fine.
4. Here is the "FUN" part. Now I went to Portfolio Analyzer. Check this
screenshot:
http://tinypic.com/f0qddx.jpg
Created an ad-hoc report using work in data area & Resource & Time (in
Month) as other two axes. I From Resource dropdown I select only the resource
in this question, & in Time dropdown I selected Last Quarter of 2005 & first
Quarter of 2006 (Oct2005 to Mar 2006).
Here we have more fun. The graph shows only Oct to Dec 2005 data & not
doesn't even show months of 2006. The total work for resource is shown as
328.4h.
I can see that OLAP cube ran successfully last night. I've set 10/2005 to
06/2006 as the fixed ranges in cube settings.
My question is what is wrong with cube or MS Project? Is there anything Im
missing here? What can cause such thing & how to fix it?
We are using Project Server 2003 with SP1 on Win2003.
Here are the details:
1. Resource A is assigned to different projects. Check this screenshot
http://tinypic.com/f0qd7o.jpg
We go to Resource Usage view, change the timescale to year / month. Now we
can see the resource's work hours by month (October 2005 - MArch 2006). He
has been assigned total of 854.25h in total. You can see that he has been
assigned 161, 152, 168 hours of work in Jan, Feb & march respectively.
2. Next I went to PWA > Resources > View Resource Assignments. Check this
screenshot
http://tinypic.com/f0qbgx.jpg
I selected the same resource in Summary view. Now I can see his work across
all plans for all months. Which is 856.88h. Thats fine.
3. Next I went to PWA > Resources > View Enterprise Resources in Resource
Center. Check this screenshot:
http://tinypic.com/f0qdcn.jpg
In Assignment work by Resource view I entered time period from 10/1/2005 to
03/31/2006. In details table below I can see his work as 854.2h, which is
fine.
4. Here is the "FUN" part. Now I went to Portfolio Analyzer. Check this
screenshot:
http://tinypic.com/f0qddx.jpg
Created an ad-hoc report using work in data area & Resource & Time (in
Month) as other two axes. I From Resource dropdown I select only the resource
in this question, & in Time dropdown I selected Last Quarter of 2005 & first
Quarter of 2006 (Oct2005 to Mar 2006).
Here we have more fun. The graph shows only Oct to Dec 2005 data & not
doesn't even show months of 2006. The total work for resource is shown as
328.4h.
I can see that OLAP cube ran successfully last night. I've set 10/2005 to
06/2006 as the fixed ranges in cube settings.
My question is what is wrong with cube or MS Project? Is there anything Im
missing here? What can cause such thing & how to fix it?