G
GreenMonster
I have a task with the following info:
Duration = 1day?
Work = 4hrs
Start = 10/16/06
Finish = 10/16/06
I completed the work today (10/11/06) and it took only 15 mins. I put .25
hrs in the "Actual Work" column and then change the "% Complete" in the task
info to 100%, the "Actual Work" then changes back to 4hrs instead of .25hrs.
Why doesn't "Actual Work" retain the .25hrs that it took to complete the task?
Duration = 1day?
Work = 4hrs
Start = 10/16/06
Finish = 10/16/06
I completed the work today (10/11/06) and it took only 15 mins. I put .25
hrs in the "Actual Work" column and then change the "% Complete" in the task
info to 100%, the "Actual Work" then changes back to 4hrs instead of .25hrs.
Why doesn't "Actual Work" retain the .25hrs that it took to complete the task?