I am calculating end dates, considering holidays.
I also have an "IF" in the formula.
Cell F17 has the following:
=IF(D17=1,E17,WORKDAY(E17,D17,$D$92:$D$97)-1)
When the number of days in cell d17 is '5' the workday returned is always
off by 2 days. In this case the start date is 11/2/2009 and duration is 5
days. the finish date should return 11/6/2009 but instead returns 11/8/2009.
This is consistant whenever I have 5 days.
Can anyone explain what I am doing wrong. All of my other Worday functions
are correct in this sheet.
I also have an "IF" in the formula.
Cell F17 has the following:
=IF(D17=1,E17,WORKDAY(E17,D17,$D$92:$D$97)-1)
When the number of days in cell d17 is '5' the workday returned is always
off by 2 days. In this case the start date is 11/2/2009 and duration is 5
days. the finish date should return 11/6/2009 but instead returns 11/8/2009.
This is consistant whenever I have 5 days.
Can anyone explain what I am doing wrong. All of my other Worday functions
are correct in this sheet.