E
Elena
Good Morning--
I found a couple of formulae on page 22 of this forum, but
cannot determine exactly how to make them work.
The situation is thus:
Enter a date that a program is due to enter testing or
whatever. The dates for all steps due before the move date
are automatically calculated and entered into cells.
I have it working with the WORKDAYS function, but was just
told that Saturdays must be included.
I tried entering all the serial numbers of all Sundays in
2004 into my Holiday array, but I can't figure out how to
make the straight date calculation look it up, and if the
calculated date lands on one of those days, to add 1 to
the date that is then inserted into the cells.
Any ideas would be greatly appreciated. And if you could
add a note explaining where I need to indicate cells in
the formula, I would be forever in your debt!
Thanks in advance.
Elena
I found a couple of formulae on page 22 of this forum, but
cannot determine exactly how to make them work.
The situation is thus:
Enter a date that a program is due to enter testing or
whatever. The dates for all steps due before the move date
are automatically calculated and entered into cells.
I have it working with the WORKDAYS function, but was just
told that Saturdays must be included.
I tried entering all the serial numbers of all Sundays in
2004 into my Holiday array, but I can't figure out how to
make the straight date calculation look it up, and if the
calculated date lands on one of those days, to add 1 to
the date that is then inserted into the cells.
Any ideas would be greatly appreciated. And if you could
add a note explaining where I need to indicate cells in
the formula, I would be forever in your debt!
Thanks in advance.
Elena