Hi
I have configured my Project Server 2007 to enable workflows
Server settings- additional server settings- project state field is set to yes

When i try to create a new proposal i dont get workflow part in the New
proposal page. Even if i log on as proposal reviewer i cannot change the
state of the proposal.

M i missing something please guide.

Secondly if i assign a task to a team of resources, then the person who is
the first one to accept to work on task and update progress.
Rest of the people then cannot even see the task in teh task page.
Is this how team assignment works or again i am missing something

Thanks for help
 