The project I am working on requires travel on a saturday, and go-live on a
Sunday.
The only way to force project 2007 to accept this is make the task - Must
End on the saturday. This is fine as long as the project does not split in
time. How do I do this without imposing this criteria. (Sat and Sun normally
a non-working day).
Also I have a training course running from tues to Sat (5 days) - must end
on Sat on task - but I have to show the task as running as 4 days to make the
ghannt chart look correct - as If I leave as 5 days it schedules in the
Monday?
Help please
Sunday.
The only way to force project 2007 to accept this is make the task - Must
End on the saturday. This is fine as long as the project does not split in
time. How do I do this without imposing this criteria. (Sat and Sun normally
a non-working day).
Also I have a training course running from tues to Sat (5 days) - must end
on Sat on task - but I have to show the task as running as 4 days to make the
ghannt chart look correct - as If I leave as 5 days it schedules in the
Monday?
Help please