J
Jackie
I work for an organization which does not work from the basic 8:00am to
5:00pm calendar. Our working times are 7:45am to 4:15pm, and I know that
Project automatically defaults to the 8:00am to 5:00pm calendar. Now I
understand how to change the Standard working calendars, and I also know how
to create a new calendar with a different name to reflect our working times,
but I noticed that once I linked 2 different different projects to the same
common resource pool and changed the default working times, everything
immediately went into red overallocations. What are suggestions on the best
way to deal with the calendar for our organization?
5:00pm calendar. Our working times are 7:45am to 4:15pm, and I know that
Project automatically defaults to the 8:00am to 5:00pm calendar. Now I
understand how to change the Standard working calendars, and I also know how
to create a new calendar with a different name to reflect our working times,
but I noticed that once I linked 2 different different projects to the same
common resource pool and changed the default working times, everything
immediately went into red overallocations. What are suggestions on the best
way to deal with the calendar for our organization?