Working Days

A

Adenrele

Hi I am trying to make a particular saturday a working day. I know I
can change the global template but that's not want I want. I want to
change just 1 saturday and enable employees enter their time for that
day.

Thanks,
 
D

Dale Howard [MVP]

Adenrele --

First of all, what version of Project Server are you using? 2002, 2003, or
2007?

Second, if you want to make the Saturday a working day, you must change it
to a working day on the enterprise Standard calendar in your Project Server
system. This is assuming that the enterprise Standard is set as the Project
Calendar (Project - Project Information) in each enterprise project. The
way you change the Standard calendar depends on your version of Project
Server.

Third, even if you did not make Saturday a working day, your team members
can still enter time on the Saturday in question. In the My Tasks page in
PWA, team members can enter Actual Work on any day of the week, including
weekends and holidays, as needed. Hope this helps.
 