working days

P

peggy

For my project, working time is 7 days a week. How do I set this up for my project? I have already started entering tasks and dates, and I have tried to "change working time" in the Tools menu, but it doesn't seem to change it from 5 days a week. Thanks.
 
J

Jan De Messemaeker

Hi Peggy,
It does.
In Tools, Cjhange Workng time, select all days of the week (in the calendar
header), click working time.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
peggy said:
For my project, working time is 7 days a week. How do I set this up for my
project? I have already started entering tasks and dates, and I have tried
to "change working time" in the Tools menu, but it doesn't seem to change it
from 5 days a week. Thanks.
 
P

peggy

I don't see where to select all the days of the week in the calendar header, or an option to click working time??? I'm using Project 2003.
 
G

Gérard Ducouret

Hello Peggy,

- Tools / Change Working time : select all the 7 columns from the M of
Monday to the S of Sunday (if your weeks begin on
monday) and click on the right pane the Working day option.
- Tools / Options / Calendar : set Hours by day = 8 and Hours by Week = 58
h...

Hope this helps,
Tell us if you found it !

Gérard Ducouret


peggy said:
I don't see where to select all the days of the week in the calendar
header, or an option to click working time??? I'm using Project 2003.
 
M

Mike Glen

Hi Peggy,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 
D

Dale Howard [MVP]

Support --

If you can help this person, then why don't you post the answer in the
newsgroup so that everyone can benefit? This newsgroup is a forum where we
all help one another publicly. I would suggest you start posting some real
answers instead of merely advertising your services.




support said:
I am from the MS Project / Project Server 2002/2003 support department at
http://www.enterpriseprojectconsulting.com and we would be happy to assist
you in resolving your issue.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top