L
Lynn
Hi all,
I have a project with a linked resource pool which was
origionally setup with working hours of 8hr per day (40
hrs per week).
After all the information has been input, I now have had
to change the working hours down to 7.5 per day (37.5 per
week)
Project is really struggling to accommodate this change. A
1d task assigned to 1 resource gives me: 100% at 40h, if I
change the resource to 37.5 hrs I get 107%
If I change the resource info to 100% and 37.5 hrs the
task duration is then less than 1 day.
HOWEVER ... if I remove the resource and reapply the
information is inserted correctly.
New tasks are always correct.
This is all working with the same project file.
Help!
I have a project with a linked resource pool which was
origionally setup with working hours of 8hr per day (40
hrs per week).
After all the information has been input, I now have had
to change the working hours down to 7.5 per day (37.5 per
week)
Project is really struggling to accommodate this change. A
1d task assigned to 1 resource gives me: 100% at 40h, if I
change the resource to 37.5 hrs I get 107%
If I change the resource info to 100% and 37.5 hrs the
task duration is then less than 1 day.
HOWEVER ... if I remove the resource and reapply the
information is inserted correctly.
New tasks are always correct.
This is all working with the same project file.
Help!