K
Keri
I wonder if someone can shed some light on this problem I
have with changing the standard working hours it's driving
me potty.
I create a new project, no tasks have been inputed yet as
the first thing i want to do is change the project
calendar. The project calendar states that our working
hours are 8:00-17:00 but i want them to be 9:00-17:00. I
will be entering tasks that have durations of 1 hour, 30
minutes etc. so it is quite important that i change the
working hours.
I am choosing Tools - Change working time - Options -
changing the working hours from 8 to 9am and the hours per
day and per week and clicking set as default but when i go
back into my calendar all of the days are stil showing as
an 8am start unless i highlight them all and change them.
Is this right?
I tried to create a new base calendar but it just adopted
the same 8am start of the standard one??
Help help I'm going insane!!
Thanking you in anticipation.
Keri
have with changing the standard working hours it's driving
me potty.
I create a new project, no tasks have been inputed yet as
the first thing i want to do is change the project
calendar. The project calendar states that our working
hours are 8:00-17:00 but i want them to be 9:00-17:00. I
will be entering tasks that have durations of 1 hour, 30
minutes etc. so it is quite important that i change the
working hours.
I am choosing Tools - Change working time - Options -
changing the working hours from 8 to 9am and the hours per
day and per week and clicking set as default but when i go
back into my calendar all of the days are stil showing as
an 8am start unless i highlight them all and change them.
Is this right?
I tried to create a new base calendar but it just adopted
the same 8am start of the standard one??
Help help I'm going insane!!
Thanking you in anticipation.
Keri